Portfolio Management · Introduction to Risk ManagementOFFICIAL

Which of the following is the correct sequence of events for risk governance and management that focuses on the entire enterprise? Establishing:

Arisk tolerance, then risk budgeting, and then risk exposures.
Brisk exposures, then risk tolerance, and then risk budgeting.
Crisk budgeting, then risk exposures, and then risk tolerance.

Explanation

In establishing a risk management system, determining risk toler- ance must happen before specific risks can be accepted or reduced. Risk toler- ance defines the appetite for risk. Risk budgeting determine how or where the risk is taken and quantifies the tolerable risk by specific metrics. Risk exposures can then be measured and compared against the acceptable risk.