The most likely impact from the cash-flow timing considered by Soroka is that:
Explanation
The forecasted timing of cash flow is an important factor affecting both projects’ IRR and NPV. In the case of delaying all future cash flows from both projects by six months, the result would be a lower IRR and a lower NPV. Given that all future cash flows are to be received six months later, their present value decreases; hence, the NPV and IRR of an entire project also decrease. B is incorrect because when cash flows from the investment projects are delayed by six months, both projects’ NPV and IRR would decrease, not stay unchanged. C is incorrect because when cash flows from the investment projects are delayed by six months, both project’s NPV and IRR would decrease.